Bjåstad Power Plant

Writer: Norhard ASNorhard AS

For Småkraft AS, Norhard supplies part of a pressure shaft to Bjåstad power plant.

This part of the pressure shaft about 630m, is carried out with Ø800mm. On August 5, roughly 1.5 months after the drilling started in mid-June. The NDL machine is now rigged down before the ND machine is erected in order to carry out reaming to Ø800mm.







 
 
 